Friday, February 20, 2015

A Bathroom Remodel--Day-by-Day--Day Eleven

A Bathroom Remodel--Day-by-Day
Day Eleven
Thursday, Feb. 19th.


    So-so-so-so-so-so-so-so close! Yet, no banana. We came, we saw, we did not finish. We still must buff the tile, hang the grab bars and the seat, touch up the paint, and install the glass panel. Like I said--close. If we'd have had Friday, as originally proposed, we'd have done it. 
    Looking at the bright side, I'm pretty good at estimating how long a job will take to accomplish. I said two weeks, and that's exactly what it would have been. So, future customers--please don't try and rush the end date. It is what it is. I even brought in some extra help last weekend, and all I got was Kirk and Steve being mad at me.     
    It won't do me any good to criticize our speed--the guys and I all agree that there are "wait times" involved with tile, and they should be followed. Most tile setters I've known don't wait. They apply mastic or thin set, lay the tile, grout them in, and buff them, all on the same day. The problem is--both the thin set and the mastic containers have the directions printed on them, and both say to wait 24 hours before grouting. This is to allow a chemical process to take place, to let certain chemicals evaporate. It will not take place if we grout and seal the tile too soon. So, over the years, I've beat it into the guys to wait. Now, no matter what I say, they wait. Am I a good teacher, or what?
    The customer not only took a day away from us, he changed his mind at the last minute and asked for a different toilet paper holder and towel bar than the ones I had bought. Not a big thing, but it does slow us down to leave the job to purchase two of the items I bought before we started the job. He didn't like the ones with the grab bars built-in--he wanted the plain, old-fashioned type. I don't blame him, but, personally, I kind-of like the grab-bar-idea. I may try them out in my bathroom. Heck--I now own them--why not use 'em. In other words, make lemonade out of lemons.
    So . . . we can't get back in the house for 13 days--March 4th. I'll be back, folks--on March 4th, to tell you we finished and show you the final photos. Thanks for joining us for the ride.
    Here are the last pictures I took--yesterday afternoon. Enjoy. 
Kirk grouting.

The floor is covered with grout--before it's cleaned off. 

A shower to be proud of.

Like I said--"Close, but no banana."

Until we meet again,
Earl.